Contract 24-101

  • Walden/Nordic Area (Reconstruction)

Contacts:

Contract 24-102

  • The Landings Area (Reclamation)
  • Oak Leaf Area (Reclamation)
  • Morgan Ave Area (Reclamation)
  • Gateway Area (Rehabilitation)

Contacts: 

Types of street improvements:

Reconstruction work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, water main replacement, and replacement of curbs.

Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Rehabilitation work consists of replacing the top 2" of pavement and minor utility work.

Maintenance Overlay work consists of replacing the top 1.5" of pavement and limited utility work

Project Updates:

Look here for weekly updates to each project area during construction.  All updates are subject to change due to weather or other circumstance.

June 6, 2025 - Nordic/Walden Areas

  • Additional reseeding was completed this week, with additional work being completed the week of 6/8. Twice daily watering of 30 minutes in the newly seeded areas is encouraged to help ensure the best possible results for your lawn.

November 4, 2024 - All Project Areas

24-101 - Project Phasing Map

  • Work is substantively completed in all project areas
  • Nordic/Walden area, pending weather, will see touch up topsoil and seeding in areas that were disturbed by driveway and mailbox work
  • If you have a damaged irrigation or a damaged pet fence, please reach out to Charlie Gerk at Charlie.Gerk@burnsvillemn.gov or 952-895-4544 for information on how to be reimbursed for repairs completed by your irrigation professional. This work can be completed in the spring of 2025 if needed
  • As previously communicated, the City and its contractor will not be responsible for any repairs to landscaping besides turf, you are now free to begin your landscaping restoration

If you would like to receive update notifications via email and/or text, please click on the 'Subscribe' button near the top of this page and fill out the required information.

Special Assessment Payments

The interest free pre-payment period began on May 8th and will be available through 11/15/2024. There are three payment options:

Assessments not paid by 11/15/2024 will be sent to Dakota County Taxation for certification to your 2025 property taxes.

Please call Molly at 952-895-4495 with any questions.

Proposed Timeline

  • February 21, 2023: Council ordered preliminary report for the 2023 Street Improvement Projects
  • March - November 2023: Staff studied project areas and drafted a preliminary report
  • October 10, 2023: Open house at Nordic Park
  • October 11, 2023: Open house at City Hall
  • December 2023: Council to receive preliminary report and call for public improvement hearing
  • February 6, 2024: Council to hold public improvement meeting
  • March 2024: Receive bids
  • April 2024: Council to hold assessment hearing and award contracts
  • May - October 2024: Construction
  • November 15, 2024: Assessment pre-payment deadline
  • Spring 2025: Final completion

Dates are tentative and subject to change.