2026 Street Improvement Projects

Construction Updates

Look here for weekly updates to each project area during construction. All updates are subject to change due to weather or other circumstances.

View interactive maps of our projects


Reconstruction

work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, water main replacement, and replacement of curbs.

Reclamation

work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Rehabilitation

work consists of replacing the top 2" of pavement and minor utility work

Special Assessment Payments

The interest free pre-payment period began on May 6th and will be available through 11/15/2026. There are three payment options:

Assessments not paid by 11/15/2026 will be sent to Dakota County Taxation for certification to your 2026 property taxes.

Please call Molly at 952-895-4495 with any questions.

Project Timeline

  • April 8, 2025: Council ordered preliminary report for the 2026 Street Improvement Projects
  • May - November 2025: Staff studied project areas and drafted a preliminary report
  • September 30, 2025: Open House at City Hall
  • October 8, 2025: Open House at North River Hills Park
  • December 16, 2025: Council to receive preliminary report and call for public improvement hearing
  • February 3, 2026: Council to hold Public Improvement Hearing
  • March 2026: Receive bids
  • April 7, 2026: Council to award construction contracts
  • May 5, 2026: Council to hold assessment hearing
  • May - October 2026: Construction
  • November 15, 2026: Assessment pre-payment deadline
  • Spring 2027: Final completion

Dates are tentative and subject to change.