2023 Street Improvement Projects

This Project Includes

Contract 23-101

  • Grand Avenue Area
  • Nicollet Avenue Area
  • Marcin Hill Area

Contacts:

Contract 23-102

  • Country Wood Estates Area
  • Sunset Terrace Area
  • Ville Du Parc Area
  • Villaburne Area

Contacts: 

Reconstruction work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, water main replacement, and replacement of curbs.

Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Rehabilitation work consists of replacing the top 2" of pavement and minor utility work.

Maintenance Overlay work consists of replacing the top 1.5" of pavement and limited utility work

Project Updates:

Look here for weekly updates to each project area during construction

June 2, 2023

Contract 23-101

  • Nicollet Avenue area: work schedule is TBD
  • Grand Avenue area: In the area that is south of CR-42, curb replacement is ongoing as well as tree and fence removal in preparation for the trail to be constructed on the west side of Grand Avenue
  • Marcin Hill area: During this pas week - curb replacement, fire hydrant replacement, and underground utility work was occurring and will continue into next week

Contract 23-102

  • Ville Du Parc area: Work in this area is substantially complete
  • Country Wood Estates area: 
    • Temporary water systems were tested and will be operational next week - notices were placed on the front doors of affected homes
    • Pavement and curb removals in the watermain replacement area will occur on Friday 6/2 or Saturday 6/3 in preparation for the watermain replacement that will be occurring the week of 6/5
  • All other areas: work scheduled is TBD


If you would like to receive update notifications via email and/or text, please click on the 'Subscribe' button near the top of this page and fill out the required information.

Special Assessment Payments

The interest free pre-payment period begins the day after City Council approves the assessments, which is tentatively scheduled for the April 18th meeting, and will be available through 11/15/2023. There are three payment options:

Assessments not paid by 11/15/2023 will be sent to Dakota County Taxation for certification to your 2024 property taxes.

Please call Molly at 952-895-4495 with any questions.

Interactive Web Map (coming soon)

Image does not exist

Proposed Timeline

  • February 22, 2022: Council ordered preliminary report for the 2023 Street Improvement Projects
  • March - November 2022: Staff studied project areas and drafted a preliminary report
  • Sept. 28, 2022: Open house at Terrace Oaks Park
  • October 5, 2022: Open house at City Hall
  • December 2022: Council to receive preliminary report and call for public improvement hearing
  • February 2023: Council to hold public improvement meeting
  • February/March 2023: Receive bids
  • April 2023: Council to hold assessment hearing and award contracts
  • April - October 2023: Construction
  • November 15, 2023: Assessment pre-payment deadline
  • Spring 2024: Final completion

Dates are tentative and subject to change.