Lake Marion Trail

This Project Includes

  • Installation of new paved trails from Sunset Pond Park to Kelleher Park
  • Installation of a new boardwalk through part of Kelleher Park
  • Installation of off-street sidewalks from Kelleher Park to Savage
  • Installation of dedicated on-street bike lanes from Kelleher Park to Savage

Contacts

Links


Updates

See updates below by phase

Phase 1

  • Paving is complete
  • Grading and restoration adjacent to the trail is under way

Phase 2

  • Paving is complete
  • Grading and restoration adjacent to the trail is under way

Phase 3

  • Grading is continuing

Phase 4

  • Schedule yet to be determined

Phase 5

  • Grading is continuing until complete
  • Paving the trail is tentatively scheduled for early-October 2020
Lake Marion Trail Phasing Map