Highland View Area

Overview

Reconstruction (northern half) consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs. Reclamation (southern half) consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Contacts

Links

Updates:

* You can also click on the map below for additional information

October 10, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): Sodding is nearly complete. Remaining sod will be placed the week of October 14, 2019, weather permitting.
  • Phase 3 (Reclamation Areas): Final paving has been delayed to the week of October 14, 2019 due to weather.
  • Phase 4 (Highland View Avenue, Lane, and Circle): Curb installation is tentatively scheduled for Friday, October 11, 2019 and Saturday, October 12, 2019. Grading is scheduled late in the week of October 14, 2019. Paving the first layer of asphalt is anticipated for the week of October 21, 2019.

October 4, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): Sodding is tentatively scheduled for the week of October 7, 2019.
  • Phase 3 (Reclamation Areas): A pedestrian ramp will be reinstalled soon at 121st Street and Connelly Drive. Final paving of streets is tentatively scheduled for Saturday, October 12, 2019.
  • Phase 4 (Highland View Avenue, Lane, and Circle): The contractor is completing water service connections. Please pay attention for door notification flyers. Curb installation is scheduled late in the week of October 7, 2019 and will continue into the week of October 14, 2019 till complete. Paving the first layer of asphalt is tentatively scheduled for early in the week of October 22, 2019.